- Completion Date
- July 2013
- Contracting Entity
- Coconino Public Works
This project consisted of 5,224 CY of excavation and a new TRM lined channel adjacent to an existing subdivision. The channel improved drainage to an area affected by storms related to the Schultz fire. We were able to complete the project in two months by properly managing the construction and by working long hours, six and seven days a week to avoid the peak monsoon season. We successfully communicated with the team (Coconino County, Forest Service, Civiltec Engineering, and NRCS) including the residents to update project status, discuss and resolve any concerns. We received numerous accolades from the residents for our professionalism, diligence and open communications.