- Completion Date
- January 2014
- Contracting Entity
- APS
TCC moved over 1.8 million cubic yards of material to mitigate potential flooding issues at the Palo Verde Nuclear Generating Station. We started this project on 7/30/12 and worked 24/7 and completed the project on 10/12/12, nearly a month ahead of schedule and within budget. This project was an example of teamwork, partnering and cooperation with all involved.