TCC provided design and construction services for this CMAR project for the City of Sedona involving rock excavation, installation of a new sewer mainline and services, sewer manholes, storm drain installation and improvements, drainage restoration, and reconstruction of existing roadways. Working closely with the residential community and the City of Sedona, we successfully installed approximately 26,000 LF of new sewer line with 358 services, manholes, and just over 4,000 LF of new storm drains and structures. The project was located in a residential area and easements with narrow access. Once sewer and storm drain installation were complete, the road throughout the subdivision was repaved.