- Completion Date
- July 2020
- Contracting Entity
- APS
The scope of work for this project consisted of creating a new 825′ x 540′ evaporation pond, and extending the existing 20′ channel over 1800′. On this project there was over 100,000 CY of excavation, installation of liner, inflow piping and electrical work.