Tiffany Construction Projects

Coconino County On-Forest Watershed Restorations
Project: Coconino County On-Forest Watershed Restorations
Project Type
Project Description
- Completion Date
- Fall 2026
- Contracting Entity
- Coconino County
These projects consisted of over 3000 LF of 72″ diameter CMP, building multiple styles of concrete channels, box culverts and utility relocates. Tiffany worked with Coconino County and their multiple design firms to get all of the materials delivered, pipe installed, channels and structures built, before the first big rain since the projects inception. Our crews worked long days, due to the importance of getting these projects completed, as the nearby homes have seen flooding breaching into their houses.
These projects consisted of repairing and bulding multiple watersheds in Flagstaff. Some of these project locations included the Wupatki/Lenox Watershed, Brandis/Thames Watershed, North and South Paintbrush, and others. Throughout these locations Tiffany has, and will continue to build mutliple alluvial fans, single and double rock sills of various sizes, and weirs. These systems help control the water as it runs off the mountain, and into additional drainage improvements surrounding the neighborhoods.


Coconino County Off-Forest Flood Mitigation
Project: Coconino County Off-Forest Flood Mitigation
Project Type
Project Description
- Completion Date
- Fall 2023
- Contracting Entity
- Coconino County
These projects consisted of over 3000 LF of 72″ diameter CMP, building multiple styles of concrete channels, box culverts and utility relocates. Tiffany worked with Coconino County and their multiple design firms to get all of the materials delivered, pipe installed, channels and structures built, before the first big rain since the projects inception. Our crews worked long days, due to the importance of getting these projects completed, as the nearby homes have seen flooding breaching into their houses.


Spruce Avenue Wash Improvements
Project: Spruce Avenue Wash Improvements
Project Type
Project Description
- Completion Date
- December 2022
- Contracting Entity
- Coconino County
This project consisted of installation of a channel, consisting of both shotcrete and concrete channels, in a highly congested neighborhood in Flagstaff, Arizona, that has seen some an excessive amount of flooding.


The Phoenician
Project: The Phoenician
Project Type
Project Description
- Completion Date
- September 2022
- Contracting Entity
- Replay
This project consisted of 51 individual lots, as well as 6 other large buildings and an interior roadway, all pushing against Camelback Mountain. With over 200,000 CY of rock excavation, Tiffany also performed all of the onsite utilities and drainage structures.


Sedona Shadows
Project: Sedona Shadows
Project Type
Project Description
- Completion Date
- October 2021
- Contracting Entity
- MHC Sedona Shadows LLC
The work consisted of building 10 new pads in Sedona, Arizona. The excavation was performed in Rock and required the use of hammers for the building pads, as well as the detention basin and utilities.


Thunder Mountain Drainage Improvements
Project: Thunder Mountain Drainage Improvements
Project Type
Project Description
- Completion Date
- July 2020
- Contracting Entity
- Coconino County
This project consisted of multiple utility relocates including multiple water and sewer lines. Tiffany crews also installed over 1850 LF of CMP drainage pipe, in a tight area of a subdivison, adjacent to Thunder Mountain Road.


Arlington Valley Evaporation Pond C
Project: Arlington Valley Evaporation Pond C
Project Type
Project Description
- Completion Date
- July 2020
- Contracting Entity
- APS
The scope of work for this project consisted of creating a new 825′ x 540′ evaporation pond, and extending the existing 20′ channel over 1800′. On this project there was over 100,000 CY of excavation, installation of liner, inflow piping and electrical work.


Flagstaff Ranch Estates
Project: Flagstaff Ranch Estates
Project Type
Project Description
- Completion Date
- June 2020
- Contracting Entity
- The Ranch Estates
A subdivision in Flagstaff, Arizona, the Estates was a project that had 16 individual 10 acre parcels within Forest Highlands. Work consisted of clearing and grubbing while maintaining as much of the existing vegetation as possible, installation of a new private roadway with drainage structures, including ditches and culverts, the installation of guardrail, retiaining walls, and an 80′ long bridge.


Westpark Wickenburg ELS
Project: Westpark Wickenburg ELS
Project Type
Project Description
- Completion Date
- May 2020
- Contracting Entity
- MHC Westpark
The scope of this work consisted of building 24 individual lots, with 20′ wide roadway, and drainage improvements using retention basins with over 25′ high slopes. This project was completed in Wickenburg, Arizona.


APS WR 45 Acre Leak
Project: APS WR 45 Acre Leak
Project Type
Project Description
- Completion Date
- April 2020
- Contracting Entity
- APS
The scope of work consisted of cleaning the slopes for a liner inspection, the installation of rub sheets for equipment and worker access. The water thatwas contained in the 45 acre reservoir was pumped into an adjacent 85 acre reservoir, while providing support for the survey of removed fish. Repairing of the liner and the installation of new inflow piping were completed.


Juniper Area Drainage Improvements
Project: Juniper Area Drainage Improvements
Project Type
Delivery Method
- Job Order Contracting (JOC)
Project Description
- Completion Date
- July 2019
- Contracting Entity
- City of Sedona
This project for the City of Sedona consists of installation of approximately 1000 lf of 42″ CMP & SRP with a small portion of 36″ CMP installation to improve drainage along Juniper Lane. Complete roadway reconstruction will complete the project in July 2019.


Coffee Pot Drainage Improvements
Project: Coffee Pot Drainage Improvements
Project Type
Delivery Method
- Job Order Contracting (JOC)
Project Description
- Completion Dates
- Little Elf Phase – June 2019
- Sanborn Crossing – June 2018
- Grasshopper Phase – June 2018
- Coffee Pot Crossing – March 2017
- Coffee Pot Phase – 2016
- Contracting Entity
- City of Sedona
We are currently constructing the third of four phases of this JOC Project. On the previous two phases, we have installed 749 lf of 72” SRP + CMP at depths of 20’, 130 lf of 48” CMP, 10’ diameter inlet drop structures and new channel grading and rip rap.


Thousand Trails Site Expansion
Project: Thousand Trails Site Expansion
Project Type
Project Description
- Compleition Date
- May 2019
- Contracting Entity
- Equity Lifestyles
We were contracted to construct 62 new RV sites at Thousand Trails RV Park for their park expansion. This included the relocation and installation of approximately 4000 lf of new sewer mainline and services, 4000 lf of electrical conduit and approximately 100 lf of new water main line and services.


Seven Canyons - Parcels B & C
Project: Seven Canyons - Parcels B & C
Project Type
Project Description
- Completion Date
- August 2018
- Contracting Entity
- Specialty/Sedona Loan Holdings, LLC
This new 55 lot subdivision in the exclusive Seven Canyons Resort consisted of 73,750 cy of earthwork, including drill and shoot and hard rock excavation in addition to demolition of existing structures, 1,167 lf of storm drain ranging from 18” to 42” diameter, 620 cy of rip rap, 2,783 lf of gravity sewer main, 2,383 lf of gas main, 3,124 lf of dry utility trench and conduit, 5,010 lf of concrete curb, and 6,740 sy of asphalt.


Chavez Ranch Road
Project: Chavez Ranch Road
Project Type
Project Description
- Compleition Date
- April 2018
- Contracting Entity
- Chavez Ranch Road Construction Corporation
Project consists of constructing 1.2 miles of new roadway to Yavapai County Specifications including 42,300 cy of earthwork, 2642 tons of asphalt, 6807 lf of curb & gutter, 2024 lf of guardrail, MSE retaining walls, multiple box culverts and slope stabilization, 930 lf of stormdrain ranging in size from 18” to 54”


Soldier Wash Drainage Improvements
Project: Soldier Wash Drainage Improvements
Project Type
Delivery Method
- Job Order Contracting (JOC)
Project Description
- Completion Dates
- Soldier Wash Phase 4B – March 2018
- Soldier Wash Phase 4A – July 2017
- Soldier Wash Portal Phase – June 2016
- Soldier Wash Pedestrian Bridge – August 2016
- City of Sedona
- Contracting Entity
This project consists of four phases for the City of Sedona’s drainage improvement plan for Soldier’s Wash which runs through the T’laquepaque shopping village. After completing the new vehicle bridge and pedestrian bridge crossing last year, TCC has begun the rehabilitation and improvement of the channel. Beginning by clearing the channel of storm water debris, trees, brush and squaring up the wash profile, installation of RediRock and CMU block began. This block will prevent channel erosion while being aesthetically pleasing. Once the block installation is complete, the bottom of the channel will be lined with concrete furthering the erosion mitigation. These four phases included demolition, relocation of multiple sewer, water, gas and dry utilities, 4139 cy of excavation, 12,660 sf of Redi-Rock channel bank protection, 23,880 sf of 6” concrete channel bottom, 553 lf of CMU retaining walls, 55 cy of shotcrete, 226 cy of rip rap, 8’ H x 22’ W x 32’ L precast box culvert and 8 x 30 clear span corton steel pedestrian bridge and abutments. Working with the City of Sedona, T’laquepaque, Los Abrigados and El Portal management has ensured Spring Break season came and went with minimal interruption and visitor access and safety were maintained throughout all four phases.


Lavin Lane & Ghostrider Water Line Replacement
Project: Lavin Lane & Ghostrider Water Line Replacement
Project Type
Project Description
- Completion Date
- December 2017
- Contracting Entity
- Arizona Water Company
These two projects in Rimrock, Arizona, were constructed concurrently in a residential neighborhood. Between the two projects, our crews installed 2,704 lf of 6” D.I.P., 1,335 lf of 8” D.I.P, 17 gate valves, 27 water services and asphalt removal and replacement.


Coconino Hills / Slayton Ranch & C
Project: Coconino Hills / Slayton Ranch & C
Project Type
Project Description
- Completion Date
- August 2017
- Contracting Entity
- Cooper Companies, Inc.
The most recent phases of this project consisted of 42 new home sites in east Flagstaff and was completed ahead of schedule and below budget. 14,592 cy of excavation, 4,750 lf of water mainline, 5,421 lf of gas trench, 7,301 lf of dry utility trench and conduit and 13, 195 sy of asphalt paving.


Rio De Flag Restoration Improvement
Project: Rio De Flag Restoration Improvement
Project Type
Delivery Method
- Job Order Contracting (JOC)
Project Description
- Completion Date
- May 2017
- Contracting Entity
- Coconino County
TCC was awarded this project by Coconino County as part of the effort to reclaim and restore a section of the Rio De Flag natural water channel from previous industrial use. In conjunction with Coconino County and the City of Flagstaff, we are also extending the Flagstaff Unified Trail System (FUTS) through the project and adding viewshed berms and an enhanced trailhead while preserving existing archeological sites. The project entailed extensive and intricate grading of slopes and viewshed berms, setting large boulders to replicate existing rock outcroppings, erosion control including rock check dams and rip rap, pulverizing 5,550 sy of existing 10” thick asphalt, placement of 2380 sy of 4” asphalt, placement of 800 sf of 8” concrete pad, 2230 lf of fencing and gates, relocation of reclaimed water line and new valve house, drainage piping and extensive irrigation including trees and shrubs. We completed this project on budget and ahead of schedule.


Church Avenue Water Line Replacement
Project: Church Avenue Water Line Replacement
Project Type
Project Description
- Completion Date
- April 2017
- Contracting Entity
- Arizona Water Company
Located next to US 60 in Superior, this was a waterline job for Arizona Water Company. The crews have been working extraordinary in completing the job ahead of schedule. Upon arriving to the site, the foreman, Marty Garcia, and AWC decided to realign the waterline as the original plans had interferences with power poles and various land owners. Once started, the crew decided to work in sections and backfill as they went. The work consisted of putting approximately 200 LF of 4” DIP through an existing sleeve under US 60 and installing 942 lf of 6” D.I.P. water mainline across Hwy 60 and up Church Ave. This included 6” tapping sleeve, 5-6” gate valves, 5 services, abandonment with slurry fill of the existing piping, and asphalt removal and replacement.


Navajo Generating Station - Pond S-3 Reline
Project: Navajo Generating Station - Pond S-3 Reline
Project Type
Project Description
- Completion Date
- February 2017
- Contracting Entity
- Salt River Project
TCC was recently awarded a contract to re-line an existing evaporation pond at the SRP Navajo Generating Station in Page, AZ. The project entails removing sludge and liner from the existing S-3 Pond before beginning improvements. These improvements include excavating and installing leak detection piping and electrical conduits, the construction of a 22’ deep wet well, electrical connections, and pump controls before grading and installing the new updated liner system.


Generrex
Project: Generrex
Project Type
Project Description
- Completion Date
- July 2016
- Contracting Entity
- Palo Verde Generating Station
Palo Verde Nuclear Generating Station (PVNGS), the nation’s largest power producer, brought together a team with TCC as the prime contractor to start the Generrex Project in August 2014. Since the commissioning of PVNGS in the 1980’s, this project is the first substantial addition to its power block. During the two years of construction our team constructed approximately 1500 cubic yards of structural concrete including structural slabs as thick as two feet and walls as high as 23 feet. Additionally, water lines, sewer lines, and fire lines were relocated under the strict protocols required at PVNGS before asphalt paving could be completed. This project has required extensive cooperation, communication, and coordination between all team members to ensure the schedule, budget, and stringent safety guidelines were met. With over 91,000 TCC man hours invested in this project, we are proud to say not a single incident occurred.


Fairfield Inn, Flagstaff
Project: Fairfield Inn, Flagstaff
Project Type
Project Description
- Completion Date
- July 2016
- Contracting Entity
- B4 Enterprises
In 27 working days, 9,884 lf of utility trenches were cut in both limestone and basalt by our 955 Vermeer Trencher.


Solana Solar Rant Ponds F&G
Project: Solana Solar Rant Ponds F&G
Project Type
Project Description
- Completion Date
- June 2016
- Contracting Entity
- Arizona Solar One, LLC
This project of constructing evaporation ponds at the Solara Solar Facility in Gila Bend, AZ, included 73,400 cy of earthwork, processing and placement of SS-13, installation of LCRS collection piping along with grading and assistance with liner installation.


Solana Solar Plant Ponds F&G
Project: Solana Solar Plant Ponds F&G
Project Type
Project Description
- Completion Date
- June 2016
- Contracting Entity
- Arizona Solar One, LLC
TCC built and lined evaporation ponds F & G at the Solana Solar Plant in Gila Bend, AZ. Project included 73,400 cy of excavation, processing and placing SS-13, installation of LCRS collection piping and prep work for placement of liner.


Corbell Data Station Expansion
Project: Corbell Data Station Expansion
Project Type
Project Description
- Completion Dates
- Phase II – May 2016
- Phase I – 2015
- Contracting Entity
- M&W Group / Salt River Project
Tiffany’s crews completed the civil construction work for M+W on Phase II for the Salt River Project and BASELAYER prototype SRP DataStation. The project is a first-of-its-kind next-generation data center in Gilbert, Arizona. The project included potholing, communications conduit, electrical conduit, concrete pads, and a 12′ x 20′ concrete slab for a modular building.


South Paintbrush Off Forest Phase II
Project: South Paintbrush Off Forest Phase II
Project Type
Project Description
- Completion Date
- July 2014
- Contracting Entity
- Coconino Public Works
This project required new SRMP, headwalls and channel construction to abate flooding from Shultz Fire burn areas.


North Paintbrush On Forest
Project: North Paintbrush On Forest
Project Type
Project Description
- Completion Date
- July 2014
- Contracting Entity
- Coconino Public Works
This project consisted of clear and grubbing, excavation and export for drainage channels, rock rundowns, and log rundowns being created on the Coconino National Forest. TCC worked closely with the County, USFS and engineers to complete this project on time.


Alice Drive Crossing
Project: Alice Drive Crossing
Project Type
Project Description
- Completion Date
- July 2014
- Contracting Entity
- Coconino Public Works
As one of the projects designed to aid in the flood mitigation efforts of Coconino County in areas effected by the Schultz fire, TCC installed a shotcrete channel, water crossings Grade control wall, and asphalt removal and replacement.


North Paintbrush Off Forest EWP
Project: North Paintbrush Off Forest EWP
Project Type
Project Description
- Completion Date
- June 2014
- Contracting Entity
- Coconino Public Works
This project consisted of 17,631 CY of excavation and export, 2,493 LF of 60″ SRMP, Gabion Channel, Asphalt removal and replacement as well as extensive utility re-locations and a new TRM lined channel. The channel improved drainage to an area affected by storms related to the Schultz fire. We successfully communicated with the team (Coconino County, Forest Service, Civiltec Engineering, and NRCS) including the residents to update project status, discuss and resolve any concerns. We received numerous accolades from the residents for our professionalism, diligence and open communications.


Intel - CH 8
Project: Intel - CH 8
Project Type
Project Description
- Completion Date
- February 2014
- Contracting Entity
- M&W Group
This project entailed all underground mainline and services for sewer, domestic water, gas and firelines including tie-ins to existing facilities for the new CH-8 building at Intel’s Chandler Campus. We also installed storm drain, drainage structures, detention basins, and grading and paving of all roadways and parking lots.


Palo Verde Nuclear Generating Station - East Wash Diversion
Project: Palo Verde Nuclear Generating Station - East Wash Diversion
Project Type
Project Description
- Completion Date
- January 2014
- Contracting Entity
- APS
TCC moved over 1.8 million cubic yards of material to mitigate potential flooding issues at the Palo Verde Nuclear Generating Station. We started this project on 7/30/12 and worked 24/7 and completed the project on 10/12/12, nearly a month ahead of schedule and within budget. This project was an example of teamwork, partnering and cooperation with all involved.


Palo Verde Nuclear Generating Station - Evaporation Pond 1
Project: Palo Verde Nuclear Generating Station - Evaporation Pond 1
Project Type
Project Description
- Completion Date
- January 2014
- Contracting Entity
- APS
TCC moved over 2.6 million cubic yards of material to construct a 300 acre evaporation pond for the Palo Verde Nuclear Generating Station. This project included soil cement at slopes, leak detection piping, and grading and prep for new liner installation.


Lower Campbell Drainage Repair
Project: Lower Campbell Drainage Repair
Project Type
Delivery Method
- Job Order Contracting (JOC)
Project Description
- Completion Date
- Summer 2013
- Contracting Entity
- Coconino County
This project was created to remove and replace the failing gabion lined drainage channel installed during the spring/summer of 2011. Tiffany was employed to work with both county officials and the selected engineering firm (Kimley-Horn & Assoc.) on the design, constructability and budget for this project. We worked side by side with both entities providing design input and value engineering alternatives including budget reviews to insure that the project came in under budget. TCC met severe time constraints on both the design and construction phases of this project.
The project consisted of the removal and replacement of two and three-tier gabion baskets with a 6” concrete channel for the entire length of the drainage channel (2334 lf) in addition to traffic control and dust mitigation. Additionally the County requested work above and beyond the contractual scope of work, which Tiffany completed at no additional cost to the County through value engineering.
The project schedule was tight and work had to be completed prior to the monsoons. TCC placed multiple crews on the site to insure early completion. The adjacent property owners expressed their appreciation for the diligence and quality our crews maintained throughout the duration of the project. The gabion basket supplier (Macaferri) brought other gabion contractors to our site to “show them how the finished product should look”. Tiffany also assumed coordination duties with APS and Century Link for utility relocations relieving county officials from this burden.


Wupatki Trails EWP
Project: Wupatki Trails EWP
Project Type
Project Description
- Completion Date
- July 2013
- Contracting Entity
- Coconino Public Works
This project consisted of 5,224 CY of excavation and a new TRM lined channel adjacent to an existing subdivision. The channel improved drainage to an area affected by storms related to the Schultz fire. We were able to complete the project in two months by properly managing the construction and by working long hours, six and seven days a week to avoid the peak monsoon season. We successfully communicated with the team (Coconino County, Forest Service, Civiltec Engineering, and NRCS) including the residents to update project status, discuss and resolve any concerns. We received numerous accolades from the residents for our professionalism, diligence and open communications.


Papago Readiness Center
Project: Papago Readiness Center
Project Type
Project Description
- Completion Date
- 2013
- Contracting Entity
- Hayden Building Corp.
Because the project is located within an active Military Base, Drill and shoot activities were not permitted and TCC was contracted to employ our 955 Vermeer Rock Trencher to assist in the excavation of 8736 cubic yards of very dense and abrasive breccia rock for a new building pad.


San Francisco De Asis Rock Trenching
Project: San Francisco De Asis Rock Trenching
Project Type
Project Description
- Completion Date
- 2011
- Contracting Entity
- Diocese of Flagstaff
TCC trenched over 5000 LF of very dense basalt rock in Flagstaff for new waterline installation.


APS - Casner Wilderness Access Road Construction
Project: APS - Casner Wilderness Access Road Construction
Project Type
Project Description
- Completion Date
- 2011
- Contracting Entity
- Arizona Public Service
Tiffany worked with APS and the US Forest Service to improve an access road through eight miles of “Protected Wilderness” on Casner Mountain, which provided access to APS’s 750 KVA Highlines. We worked closely with the Forest service to protect the area’s environment and minimize impact while meeting the Client’s needs. During this project we encountered two feet of snow cover and faced many challenges of safely mobilizing crews and equipment to a remote site. The client was extremely pleased with the expedience and quality of the work performed and the manner in which it was accomplished.


Harmony Windsong Drainage Improvements
Project: Harmony Windsong Drainage Improvements
Project Type
Delivery Method
- Construction Manager at Risk (CMAR)
Project Description
- Compleition Date
- May 2010
- Contracting Entity
- City of Sedona
Tiffany Construction was the contractor for the Design and Construction Phases of this CM@R project. During the design phase Tiffany met with the design engineer and provided constructability reviews, value engineering and prepared estimates for best value alternates. Also, TCC prepared a master construction schedule, traffic control plan, designed and reviewed the SWPPP plan, Sub-Contractor Selection plan, attended meetings with the city and design engineer and prepared the GMP. The construction part of the project included the excavation and installation of 1,760 LF of Storm Drain Channel. The major items of work include: 251 LF of dual 78” SRMP, 154 LF of dual 72” SRMP, 332 LF of dual 72” CMP, 410 LF of dual 78” CMP, 430 LF of 142” x 91” CMPA, 125 LF of 12” through 48” CMP, 14 LF of Concrete Transition Channel, 340 SF of Concrete Channel modification, custom grated headwall, custom junction structure, concrete channel with baffles, various removals, traffic control, landscaping, SWPPP construction staking, riprap swales, AC paving at street crossings and several other miscellaneous items.
Tiffany took over as both the Design and Construction Phase Contractor for this CMAR project after the contractor selected initially was not able to meet the City of Sedona’s budget. When we became involved in the design phase of the project, the plans were at 80% complete status. This provided us an opportunity to work with the city and design engineer to incorporate value engineering options and constructability reviews in a combined effort to achieve the budgeted amount. Tiffany not only was able to meet the city’s budget but we saved the city an additional $161,410 from the GMP. Also, we prepared a master construction schedule, traffic control plan, designed and implemented the SWPPP plan, Sub-Contractor Selection plan, attended meetings with the city and design engineer, and prepared the GMP.
Tiffany received numerous accolades from the residents and property owners for our communications and processing of the job and minimizing disruptions to all concerned.


Forest Highlands Effluent Pond
Project: Forest Highlands Effluent Pond
Project Type
Project Description
- Completion Date
- January 2010
- Contracting Entity
- Coconino County
Excavating, lining and piping of a new effluent pond for Forest Highlands.


Chapel Sewer Extension and Drainage Improvements
Project: Chapel Sewer Extension and Drainage Improvements
Project Type
Delivery Method
- Construction Manager at Risk (CMAR)
Project Description
- Completion Date
- 2009
- Contracting Entity
- City of Sedona
TCC provided design and construction services for this CMAR project for the City of Sedona involving rock excavation, installation of a new sewer mainline and services, sewer manholes, storm drain installation and improvements, drainage restoration, and reconstruction of existing roadways. Working closely with the residential community and the City of Sedona, we successfully installed approximately 26,000 LF of new sewer line with 358 services, manholes, and just over 4,000 LF of new storm drains and structures. The project was located in a residential area and easements with narrow access. Once sewer and storm drain installation were complete, the road throughout the subdivision was repaved.


Lake Mary Road Improvements
Project: Lake Mary Road Improvements
Project Type
Project Description
- Completion Date
- 2009
- Contracting Entity
- Vastco Inc.
TCC trenched 14,858 LF of 6’-8’ deep trench with our T955 Vermeer Rock Trencher in basalt and limestone before installing dry utilities along Lake Mary Road. We were able to complete this project in 18 working days, below budget and ahead of schedule.


L’Auberge De Sedona
Project: L’Auberge De Sedona
Project Type
Delivery Method
- Design-Build
Project Description
- Completion Date
- January 2009
- Contracting Entity
- L’Auberge-Orchards, LLC
L’Auberge was one of our most complicated projects to date. We were tasked with managing and coordinating the construction and redesign of one of Sedona’s premier resorts while the resort remained open. This project utilized and tested the skills of our project managers and foremen. Working closely with Shephard-Westnitzer’s design team, our project manager directed our crews in rock excavation, utility installation and site construction for 36 pre-manufactured cabins added to the existing resort including 19 cabins placed on the hillside, supported by caissons as well as a two level, 150 stall parking garage while coordinating with over a dozen subcontractors who were working simultaneously.
The unique challenges encountered here included:
- Maintaining a safe environment for the resort staff and quests
- Managing a multiple activities in an extremely small area
- Safely excavating a nearly vertical rock hillside for construction of a parking garage and new units
- Addressing the daily environmental protection of Oak Creek
- Working with multiple local and state agencies and utilities
- Readjusting the schedule and approach to allow for design changes and alterations
We successfully faced each challenge while maintaining satisfaction with subcontractors, agencies and the client.


Spring Valley Road
Project: Spring Valley Road
Project Type
Delivery Method
- Job Order Contracting (JOC)
Project Description
- Completion Date
- August 2008
- Contracting Entity
- Coconino County
This project consisted of clearing and grubbing, road reconstruction (including placement of 6016 cy of borrow material to elevate the roadway), 65 lf reinforced concrete box culvert, 118 lf 33″ x 49″ CMP arch placement and grading of 969 cy of recycled asphalt pavement. TCC obtained, coordinated and supervised the survey, geotechnical and quality control functions of the project through selected qualified subcontractors in addition to the structural concrete subcontractor hired to complete the box culvert. TCC designed the traffic control and storm water pollution prevention plans. We were praised for our efforts for maintaining safe access for vehicles and pedestrians during construction. The project was completed three weeks ahead of schedule.


Dove Mountain Golf Course & Ritz Carlton at Dove Mountain
Project: Dove Mountain Golf Course & Ritz Carlton at Dove Mountain
Project Type
Project Description
- Completion Date
- April 2008
- Contracting Entity
- Cottonwood Properties
Dove Mountain Golf Course is an 18 hole Jack Nicklaus Signature Course. TCC performed as the general contractor for all earthwork. The project included a large drainage channel which was excavated and lined with soil cement, grouted and non-grouted riprap, concrete cut-off walls, and a small amount of shotcrete. The original design called for a concrete lined channel, however TCC proposed a value engineering alternate to the owner, which replaced the 6″ thick concrete channel with 48″ thick soil cement. Not only did this alternate provide a substantial cost savings, but it cut the construction schedule by two months. Our client was so impressed with our workmanship, professionalism and value engineering alternatives that they negotiated a second contract to construct an additional nine holes for Ritz Carlton at Dove Mountain. This additional project included an extension of the drainage channel.


The Links at Las Palomas
Project: The Links at Las Palomas
Project Type
Project Description
- Completion Date
- 2007
- Contracting Entity
- Forrest Richardson, Golf Course Architect
TCC built an award winning 19 hole target golf course that included 4 lakes lined with SS-13 on Sandy Beach in Rocky Point, Mexico. This project was awarded ‘2007 Development of the Year’ by Golf Inc. Magazine.


Park Place Condominiums
Project: Park Place Condominiums
Project Type
Project Description
- Completion Date
- 2007
- Contracting Entity
- Miller Bros.
TCC removed 23,663 CY of rock utilizing drill and shoot for new condo pads for a new condominium project in Sedona. In addition, we rock trenched with our Vermeer T955 Trencher and installed 2,723 LF of sanitary sewer, 2,024 LF of 8” waterline, 2,560 LF of dry utilities, 2,335 LF of gasline and 2,982 LF of stormdrain ranging in size from 12” to 48”.


Sedona Uptown Enhancement
Project: Sedona Uptown Enhancement
Project Type
Delivery Method
- Construction Manager at Risk (CMAR)
Project Description
- Completion Date
- 2007
- Contracting Entity
- City of Sedona
Working with the design engineer and the City of Sedona, we were able to trim over a million dollars from the original budgeted amount. This was a complex project regarding construction and scheduling as the project was completed while the many retail shops, restaurants and hotels remained open during peak season. Our work included asphalt paving of Hwy 89A, intricate demolition, decorative concrete sidewalks (redesigned to be ADA compliant), retaining walls, utility relocations (including coordination with various utility providers), installation of new utilities and storm drain. The project was completed on schedule and within budget, receiving numerous commendations from the City of Sedona and the merchants for our diligence, professionalism and our responsiveness to resolving potential issues.


Kachina Sewer Extension
Project: Kachina Sewer Extension
Project Type
Delivery Method
- Construction Manager at Risk (CMAR)
Project Description
- Completion Date
- August 2007
- Contracting Entity
- City of Sedona
The Kachina Sewer Extension Project for the City of Sedona involved rock excavation and trenching for the placement of new sewer lines and services within a residential community and school zone. The project included manholes, drainage and roadway reconstruction. TCC assisted in the design phase of this project by value engineering a portion of the work, cost estimating and scheduling. We self-performed 96% of the work originally scheduled for one year. TCC completed the project four months ahead of schedule, saving the City of Sedona $210,000.


Red Rock Ranger Station
Project: Red Rock Ranger Station
Project Type
Delivery Method
- General Contracting
Project Description
- Completion Date
- 2006
- Contracting Entity
- US Forest Service
This project included installation of 4424 lf of 12” Ductile water main line and approximately 4400 lf of dry utilities in a joint trench for the US forest Service at their new Red Rock Ranger District location on Hwy 179. We trenched and excavated hard rock for the installation of these utilities in the right of way adjacent to Hwy 179 located south of the Village of Oak Creek.


Serenity Shores
Project: Serenity Shores
Project Type
Project Description
- Completion Date
- 2006
- Contracting Entity
- Cachet Homes
TCC excavated and installed underground utilities for a new 47 lot subdivision at Fulton Ranch in Chandler, AZ. This project Included 3,392 LF of 8” sanitary sewer, 32 manholes, 4,133 lf of 8” DIP waterline, 4,900 LF of dry utilities and 2,106 LF of storm drain ranging from 12” to 24”.

