Located next to US 60 in Superior, this was a waterline job for Arizona Water Company. The crews have been working extraordinary in completing the job ahead of schedule. Upon arriving to the site, the foreman, Marty Garcia, and AWC decided to realign the waterline as the original plans had interferences with power poles and various land owners. Once started, the crew decided to work in sections and backfill as they went. The work consisted of putting approximately 200 LF of 4” DIP through an existing sleeve under US 60 and installing 942 lf of 6” D.I.P. water mainline across Hwy 60 and up Church Ave. This included 6” tapping sleeve, 5-6” gate valves, 5 services, abandonment with slurry fill of the existing piping, and asphalt removal and replacement.