Tiffany Construction Company

General Construction Projects

Intel - CH 8   

Compleition Date: 2/2014

Contracting Entity: M&W Group

This project entailed all underground mainline and services for sewer, domestic water, gas and firelines including tie-ins to existing facilities for the new CH-8 building at Intel’s Chandler Campus. We also installed storm drain, drainage structures, detention basins, and grading and paving of all roadways and parking lots.

L’Auberge De Sedona –    

Compleition Date: 1/15/2009

Contracting Entity: L’Auberge-Orchards, LLC

L’Auberge was one of our most complicated projects to date. We were tasked with managing and coordinating the construction and redesign of one of Sedona’s premier resorts while the resort remained open. This project utilized and tested the skills of our project managers and foremen. Working closely with Shephard-Westnitzer’s design team, our project manager directed our crews in rock excavation, utility installation and site construction for 36 pre-manufactured cabins added to the existing resort including 19 cabins placed on the hillside, supported by caissons as well as a two level, 150 stall parking garage while coordinating with over a dozen subcontractors who were working simultaneously.

The unique challenges encountered here included:
  • Maintaining a safe environment for the resort staff and quests
  • Managing a multiple activities in an extremely small area
  • Safely excavating a nearly vertical rock hillside for construction of a parking garage and new units
  • Addressing the daily environmental protection of Oak Creek
  • Working with multiple local and state agencies and utilities
  • Readjusting the schedule and approach to allow for design changes and alterations
We successfully faced each challenge while maintaining satisfaction with subcontractors, agencies and the client.

 

APS - Casner Wilderness Access Road Construction

Compleition Date: 2011

Contracting Entity: Arizona Public Service

Tiffany worked with APS and the US Forest Service to improve an access road through eight miles of “Protected Wilderness” on Casner Mountain, which provided access to APS’s 750 KVA Highlines. We worked closely with the Forest service to protect the area’s environment and minimize impact while meeting the Client’s needs. During this project we encountered two feet of snow cover and faced many challenges of safely mobilizing crews and equipment to a remote site. The client was extremely pleased with the expedience and quality of the work performed and the manner in which it was accomplished.
 

Sedona Uptown Enhancement CMAR   

Compleition Date: 2007

Contracting Entity: City of Sedona

Working with the design engineer and the City of Sedona, we were able to trim over a million dollars from the original budgeted amount. This was a complex project regarding construction and scheduling as the project was completed while the many retail shops, restaurants and hotels remained open during peak season. Our work included asphalt paving of Hwy 89A, intricate demolition, decorative concrete sidewalks (redesigned to be ADA compliant), retaining walls, utility relocations (including coordination with various utility providers), installation of new utilities and storm drain. The project was completed on schedule and within budget, receiving numerous commendations from the City of Sedona and the merchants for our diligence, professionalism and our responsiveness to resolving potential issues.