- Completion Date
- August 2008
- Contracting Entity
- Coconino County
This project consisted of clearing and grubbing, road reconstruction (including placement of 6016 cy of borrow material to elevate the roadway), 65 lf reinforced concrete box culvert, 118 lf 33″ x 49″ CMP arch placement and grading of 969 cy of recycled asphalt pavement. TCC obtained, coordinated and supervised the survey, geotechnical and quality control functions of the project through selected qualified subcontractors in addition to the structural concrete subcontractor hired to complete the box culvert. TCC designed the traffic control and storm water pollution prevention plans. We were praised for our efforts for maintaining safe access for vehicles and pedestrians during construction. The project was completed three weeks ahead of schedule.

