- Completion Dates
- Little Elf Phase – June 2019
- Sanborn Crossing – June 2018
- Grasshopper Phase – June 2018
- Coffee Pot Crossing – March 2017
- Coffee Pot Phase – 2016
- Contracting Entity
- City of Sedona
We are currently constructing the third of four phases of this JOC Project. On the previous two phases, we have installed 749 lf of 72” SRP + CMP at depths of 20’, 130 lf of 48” CMP, 10’ diameter inlet drop structures and new channel grading and rip rap.