- Completion Dates
- Phase II – May 2016
- Phase I – 2015
- Contracting Entity
- M&W Group / Salt River Project
Tiffany’s crews completed the civil construction work for M+W on Phase II for the Salt River Project and BASELAYER prototype SRP DataStation. The project is a first-of-its-kind next-generation data center in Gilbert, Arizona. The project included potholing, communications conduit, electrical conduit, concrete pads, and a 12′ x 20′ concrete slab for a modular building.