Tiffany Construction Company

Subdivisions

The Phoenician

Completion Date: September 2022

Contracting Entity: Replay

This project consisted of 51 individual lots, as well as 6 other large buildings and an interior roadway, all pushing against Camelback Mountain. With over 200,000 CY of rock excavation, Tiffany also performed all of the onsite utilities and drainage structures. 

 

 Sedona Shadows

Completion Date: October 2021

Contracting Entity: MHC Sedona Shadows LLC

The work consisted of building 10 new pads in Sedona, Arizona. The excavation was performed in Rock and required the use of hammers for the building pads, as well as the detention basin and utilities.

 

Flagstaff Ranch Estates

Completion Date: June 2020                         

Contracting Entity: The Ranch Estates

A subdivision in Flagstaff, Arizona, the Estates was a project that had 16 individual 10 acre parcels within Forest Highlands. Work consisted of clearing and grubbing while maintaining as much of the existing vegetation as possible, installation of a new private roadway with drainage structures, including ditches and culverts, the installation of guardrail, retiaining walls, and an 80' long bridge. 

 

 Westpark Wickenburg ELS

Completion Date: May 2020

Contracting Entity: MHC Westpark

The scope of this work consisted of building 24 individual lots, with 20' wide roadway, and drainage improvements using retention basins with over 25' high slopes. This project was completed in Wickenburg, Arizona. 

 

Seven Canyons - Parcels B & C

Completion Date: August 2018

Contracting Entity: Specialty/Sedona Loan Holdings, LLC

This new 55 lot subdivision in the exclusive Seven Canyons Resort consisted of 73,750 cy of earthwork, including drill and shoot and hard rock excavation in addition to demolition of existing structures, 1,167 lf of storm drain ranging from 18” to 42” diameter, 620 cy of rip rap, 2,783 lf of gravity sewer main, 2,383 lf of gas main, 3,124 lf of dry utility trench and conduit, 5,010 lf of concrete curb, and 6,740 sy of asphalt.

 

Coconino Hills / Slayton Ranch & C

Completion Date: August 2017

Contracting Entity: Cooper Companies, Inc.

The most recent phases of this project consisted of 42 new home sites in east Flagstaff and was completed ahead of schedule and below budget. 14,592 cy of excavation, 4,750 lf of water mainline, 5,421 lf of gas trench, 7,301 lf of dry utility trench and conduit and 13, 195 sy of asphalt paving.